Question: You are a project manager on a project designing a motorized toy car for children. The project team finds that a few cars can only

 You are a project manager on a project designing a motorized

You are a project manager on a project designing a motorized toy car for children. The project team finds that a few cars can only go two miles per hour, not three miles per hour. One of the requirements for the toy car is that it must go three miles per hour. What type of change request should you initiate? a) Corrective action b) Defect repair c) Preventive action d) Updates