Question: You are a project manager working on a project that uses the Predictive project management methodology. Recently, a new critical new requirement has been introduced.

You are a project manager working on a project that uses the Predictive project management methodology. Recently, a new critical new requirement has been introduced. To identify the appropriate next actions to address this change, which of the following should you refer to?A Product BacklogB Project charterC Scope management planD Project requirements documentation7 of 30 student submitted image, transcription available