Question: You are a project manager working on creating a new website, and you're beginning to develop the project schedule. You have the following information: Task

You are a project manager working on creating a new website, and you're beginning to develop the project schedule. You have the following information:
Task A takes 1 week.
Task B takes 3 weeks.
Task C takes 3 weeks.
Task D takes 5 weeks.
A and B can be started together. C needs to start after B. Tasks C and D should be started together.
How many weeks will the project take to complete?