Question: You are about to take over a project from another project manager and find out that there are eleven stakeholders on the project. Task Z

You are about to take over a project from another project manager and find out that there are eleven stakeholders on the project. Task Z has an early start of day 15 and a late start of day 20, task Z is a difficult task. The Cost Performance Index (CPI) is 1.1 and the Schedule Performance Index (SPI) is 0.8. Based on this information, which of the following would you be the MOST concerned about?
Question 13 options:
a)
Schedule
b)
Cost
c)
The number of available resources
d)
Float