Question: You are about to take over a project from another project manager and find out that there are eleven stakeholders on the project. Task Z
You are about to take over a project from another project manager and find out that there are eleven stakeholders on the project. Task Z has an early start of day and a late start of day task Z is a difficult task. The Cost Performance Index CPI is and the Schedule Performance Index SPI is Based on this information, which of the following would you be the MOST concerned about?
Question options:
a
Schedule
b
Cost
c
The number of available resources
d
Float