Question: You are analyzing a production line. There are five processes, labeled A through E , and your widgets start at Process A , then go

You are analyzing a production line. There are five processes, labeled A through E, and your widgets start at Process A, then go to Process B, C, D, and E. The process map looks a bit like this:
Start -> A -> B -> C -> D -> E -> Finish.
You have the following process information:
Process A requires 10 minutes per widget.
Process B does 4 widgets per hour.
Process C does 4.6 widgets per hour.
Process D can do 28 widgets per 8-hour shift.
Process E takes 16 minutes per widget.