Question: You are analyzing a production line. There are five processes, labeled A through E, and your widgets start at Process A, then go to Process
You are analyzing a production line. There are five processes, labeled A through E, and your widgets start at Process A, then go to Process B, C, D, and E. The process map looks a bit like this:
Start -> A -> B -> C -> D -> E -> Finish.
You have the following process information:
Process A requires 10 minutes per widget.
Process B does 4 widgets per hour.
Process C does 4.6 widgets per hour.
Process D can do 28 widgets per 8-hour shift.
Process E takes 16 minutes per widget.
You are consulting to Trains R Us as part of your corporate outreach program. Trains R Us believes that in their first month of operations their efficiency will be 50%, going up to 87% after a month in operation. If they purchase a setup for which the design capacity is 1,868 trains per month, and the effective capacity is 959 trains per month, how many trains would you expect them to be making in Month 5?