Question: You are analyzing the following two mutually exclusive projects and have developed the following information. What is the crossover rate? Year Project A Project B
You are analyzing the following two mutually exclusive projects and have developed the following information. What is the crossover rate?
Year Project A Project B
0 -75000 -75000
1 26300 24000
2 29500 26900
3 45300 51300