Question: You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has
You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished. Following your studies, the budget estimations are correct. You have performed earned value analysis and obtained the following results:
EV: 250,000; PV: 200,000; AC 275,000: BAC is 500,000.
Calculate EAC optimistically.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
