Question: You are completing the planning for a project schedule. Because you do not have much information about one activity, you decide to estimate its duration

You are completing the planning for a project schedule. Because you do not have much information about one activity, you decide to estimate its duration by referring to the actual duration of a similar activity on another project. This calculation method is called:

A. Analogous estimating

B. Expert judgment

C. Parametric estimating

D. Reserve analysis