Question: You are completing the planning for a project schedule. Because you do not have much information about one activity, you decide to estimate its duration
You are completing the planning for a project schedule. Because you do not have much information about one activity, you decide to estimate its duration by referring to the actual duration of a similar activity on another project. This calculation method is called:
| A. Analogous estimating | ||
| B. Expert judgment | ||
| C. Parametric estimating | ||
| D. Reserve analysis |