Question: You are considering 4 different projects but only need to select one of them for investment. You've evaluated these projects individually and found the following:

You are considering 4 different projects but only need to select one of them for investment. You've evaluated these projects individually and found the following: IRR(option 1) = 12.32%, IRR(option 2) = 4.57%, IRR(option 3) = 43.7% and IRR(option 4) = 9.95%. If your company's MARR is 10%, which of these projects should you consider further? O All of the projects (Options 1, 2, 3, and 4) O Projects 1, 2, and 3 only O Projects 2 and 4 only O Projects 1 and 3 only O Option 3 only O Cannot determine, need more information