Question: You are considering the following two mutually exclusive projects. The crossover point is _____ and project _____ should be accepted if the discount rate is

You are considering the following two mutually exclusive projects. The crossover point is _____ and project _____ should be accepted if the discount rate is 14 percent. 15.96 percent; B 13.28 percent; B 13.28 percent; A 15.96 percent; A 0 percent; B