Question: You are considering two mutually exclusive projects. Project A has a net present value of $11,507 and an IRR of 12.28 percent. Project B has
You are considering two mutually exclusive projects. Project A has a net present value of $11,507 and an IRR of 12.28 percent. Project B has a net present value of $10,208 and an IRR of 13.64 percent. Which project(s) should be accepted?
| |||
| |||
| |||
|