Question: You are considering two mutually exclusive projects. Project A has cash flows of-$87,000, $36,200, $35,900, and $43,400 for years 0 to 3, respectively. Project B
You are considering two mutually exclusive projects. Project A has cash flows of-$87,000, $36,200, $35,900, and $43,400 for years 0 to 3, respectively. Project B has cash flows of -$85,000, $14,700, $21,200, and $89,800 for years O to 3, respectively. Project A has a required return of 9 percent while Project B's required return is 11 percent. Which project(s), if either, should you accept based on net present value? O Accept both projects O Reject both projects 0 Reject Project A and accept Project B O accept Either one, but not both O Accept Project A and reject Project B