Question: You are considering two mutually exclusive projects with the following cash flows. If the discount rate is 7.5%, you prefer Project _____ and if the
You are considering two mutually exclusive projects with the following cash flows. If the discount rate is 7.5%, you prefer Project _____ and if the discount rate is 12%, you prefer Project _____. Year Project A Project B 0 -$320,000 -$358,000 1 $0 $330,500 2 $0 $79,500 3 $425,000 $0 Multiple Choice A; A A; B B; A B; B B; A or B as you are indifferent