Question: You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below, complete the forward and backward pass,
You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. Given the information below, complete the forward and backward pass, compute activity slack, and identify the critical path.
| ID | Description | Predecessor | Time (days) |
| A | Systems | None | 6 |
| B | Subsystem A design | A | 4 |
| C | Subsystem B design | A | 1 |
| D | Subsystem C design | A | 4 |
| E | Program A | B | 3 |
| F | Program B | C | 11 |
| G | Program C | D | 3 |
| H | Subsystem A test | E | 5 |
| I | Subsystem B test | F | 4 |
| J | Subsystem C test | G | 5 |
| K | Integration | H, I, J | 1 |
| L | Integration test | K | 3 |
\begin{tabular}{|c|c|} \hline What is the total slack on D? & days. \\ \hline What is the total slack on E? & \\ \hline What is the FREE slack on B? & \\ \hline What is the FREE slack on H ? & day(s). \\ \hline \end{tabular}