Question: You are deciding to choose between three mutually exclusive projects. a. option1: project X will cost $5000 to install and $4000 a year to run
You are deciding to choose between three mutually exclusive projects.
a. option1: project X will cost $5000 to install and $4000 a year to run and will last for three years.
b. option 2: project Y will cost $6000 to install and $3700 a year to run and will last for four years.
c. option 3: project Z will cost $10,000 to install and $400 a year to run and will last forever.
Let the WACC = 0.07
Estimate the NPV of project X.
Answer for part 1
Estimate the equivalent annuity cost of project X.
Answer for part 2
Estimate the NPV of project Y.
Answer for part 3
Estimate the equivalent annuity cost of project Y.
Answer for part 4
Estimate the NPV of project Z.
Answer for part 5
Estimate the equivalent annuity cost of project Z.
Answer for part 6
Which option would you choose option 1, 2 or 3?
Answer for part 7
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock