Question: You are developing a ance progress report you are managing the following time phase budget was developed earlier in the planning stage and is being
You are developing a ance progress report you are managing the following time phase budget was developed earlier in the planning stage and is being used as the standard against Wister project performance as measured
| Work packages.Work packages | W1 | W-2 | W3 | W-4 | W5 | W6 |
| A | 3 | 10 | 5 | |||
| B | 10 | |||||
| c | 6 | 6 | ||||
| Total | 3 | 10 | 5 | 10 | 6 | 6 |
You are analyzing the project performance at the end of week three activity a is 60% complete and its actual cost history activity B &c . have not started yet what is the to complete performance index of this project?
.