Question: You are developing a performance progress report for a project you are managing. The following time - phased budget was developed earlier in the planning

You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured.
\table[[\table[[Work],[Packages]],W1,W2,W3,W4,W5,W6,W7,W8,W9,W10,W11],[A,3,1,7,,,,,,,,],[B,,,,9,9,6,,,,,],[C,,,,,,,2,8,4,7,9],[Total,3,1,7,9,9,6,2,8,4,7,9]]
You are analyzing the project performance at the end of Week 5. Activity "B" is 40% complete and its actual cost is 15. What is the Schedule Performance Index of this activity?
Use two decimal places in your calculations.
 You are developing a performance progress report for a project you

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!