Question: You are developing a performance progress report for a project you are managing. The following time - phased budget was developed earlier in the planning

You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured.
Activities W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11
A 889
B 889
C 18712
Total 88988918712
At the end of Week 6, Activity "B" is 90% complete and its actual cost is 15. What is the Planned Value of this activity?