Question: You are developing a performance progress report for a project you are managing. The following time - phased budget was developed earlier in the planning

You are developing a performance progress report for a project you are managing. The following time-phased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured.
\table[[Work Packages,W1,W2,W3,W4,W5,W6],[A,9,6,5,,,],[B,,,,8,,],[C,,,,,8,2],[Total,9,6,5,8,8,2]]
You are analyzing the project performance at the end of Week 3. Activity "A" is 60% complete and its actual cost is 9. Activities B and C have not started yet.
What is the to-complete performance index of this project?
Use two decimal places in your calculations.
 You are developing a performance progress report for a project you

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!