Question: You are developing a performance progress report for a project you are managing. The following timephased budget was developed earlier in the planning stage and

You are developing a performance progress report for a project you are managing. The following timephased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured.
\table[[\table[[Work],[Packages]],W1,W2,W3,W4,W5,W6,W7,W8,W9,W10,W11],[A,9,1,9,,,,,,,,],[B,,,,5,5,3,,,,,],[C,,,,,,,7,2,2,1,6],[Total,9,1,9,5,5,3,7,2,2,1,6]]
You are analyzing the project performance at the end of Week 5. Activity "B" is 40% complete and its actual cost is 15. What is the Schedule Performance Index of this activity?
Use two decimal places in your calculations.
You are developing a performance progress report for a project you are managing. The following timephased budget was developed earlier in the planning stage and is being used as the standard against which the project performance is measured.
\table[[\table[[Work],[Packages]],W1,W2,W3,W4,W5,W6,W7,W8,W9,W10,W11],[A,9,1,9,,,,,,,,],[B,,,,5,5,3,,,,,],[C,,,,,,,7,2,2,1,6],[Total,9,1,9,5,5,3,7,2,2,1,6]]
You are analyzing the project performance at the end of Week 5. Activity "B" is 40% complete and its actual cost is 15. What is the Schedule Performance Index of this activity?
Use two decimal places in your calculations.
 You are developing a performance progress report for a project you

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!