Question: You are early in the evaluation process for a new natural gas power plant near Saskatoon. You have reviewed previous builds in the province and

You are early in the evaluation process for a new natural gas power plant near Saskatoon. You have reviewed previous builds in the province and similar jurisdictions. You have observed that these types of plants appear to have a cost-capacity factor of approximately 4 and that a similar plant with capacity of 350 MW has just been completed at a cost $5,000,000. How much would you expect your 425 MW capacity plant to cost?