Question: You are examining a Gantt chart. Activity A is a predecessor ( finish to start relationship ) of Activity B . On the Gantt chart
You are examining a Gantt chart. Activity A is a predecessor finish to start relationship of Activity B On the Gantt chart Activity B is planned to start exactly when Activity A finishes. There is a chance that Activity A has a free slack. True or false?