Question: You are finalizing the monthly project status report due now to your manager when you discover that several project team members are not reporting actual

You are finalizing the monthly project status report due now to your manager when you discover that several project team members are not reporting actual hours spent on project activities. This results in skewed project statistics. What is the mostappropriate action to take?
A. Discuss the impacts of these actions with team members.
B. Report the team members' actions to their functional managers.
C. Continue reporting information as presented to you.
D. Provide accurate and truthful representations in all project reports.
 You are finalizing the monthly project status report due now to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!