Question: You are finalizing the monthly project status report due now to your manager when you discover that several project team members are not reporting actual

You are finalizing the monthly project status report due now to your manager when you discover that several project team members are not reporting actual hours spent on project activities. This results in skewed project statistics. What is the MOST appropriate action to take?
Question options:
Discuss the impacts of these actions with team members
Report the team members actions to their functional managers
Continue reporting information as presented to you
Provide accurate and truthful representations in all project reports