You are given the following data for a 2-D Build & Hold well profile: Determine the total measured depth. KOP = Target TVD = Target Horizontal Departure = Build-up Rate = Maximum Hole Inclination= 2,500 ft 12,500 ft 9,200 ft 3 deg/100 ft 45 deg