You are given the following data for a project:
\table[[Activity,\table[[Expected Time],[(days)]],Critical],[A,15,YES],[B,4,NO],[C,10,YES],[D,8,YES],[E,6,NO],[F,12,YES],[G,7,YES],[H,10,NO]]
What is the expected completion time of this project?
51
55
 You are given the following data for a project: \table[[Activity,\table[[Expected Time],[(days)]],Critical],[A,15,YES],[B,4,NO],[C,10,YES],[D,8,YES],[E,6,NO],[F,12,YES],[G,7,YES],[H,10,NO]]