Question: You are given the following information about a task: ES=4, EF=10. It is its successor task's only predecessor. There is to be a delay (or
You are given the following information about a task: ES=4, EF=10. It is its successor task's only predecessor. There is to be a delay (or lag) of 8 time units between the finish of the predecessor task and the start of the successor task. What is the ES of the successor task? Select one: a.
4 b.
10 c.
12 d.
18