Question: You are given the following information about activity A: Normal time = 9 weeksCrash time = 7 weeksNormal cost = $ 2 0 , 0

You are given the following information about activity A:
Normal time =9 weeksCrash time=7 weeksNormal cost= $20,000Crash cost= $30,000
What will it cost to complete activity A in 8 weeks?
Group of answer choices
greater than $24,000 but less than or equal to $27,000
greater than $27,000 but less than or equal to $30,000
less than or equal to $24,000
greater than $30,000