Question: You are given the following information about activity A: Normal time = 9 weeksCrash time = 7 weeksNormal cost = $ 2 0 , 0
You are given the following information about activity A:
Normal time weeksCrash time weeksNormal cost $Crash cost $
What will it cost to complete activity A in weeks?
Group of answer choices
greater than $ but less than or equal to $
greater than $ but less than or equal to $
less than or equal to $
greater than $