Question: You are given the following information about activity B: Normal time = 9 weeks Crash time = 5 weeks Cost to crash per week =
You are given the following information about activity B: Normal time = 9 weeks Crash time = 5 weeks Cost to crash per week = $2000 Crash cost = $41,000 What will it cost to complete activity B in 6 weeks? A. Greater than $34,000 but less than or equal to $36,000 B. Less than or equal to $34,000 C. Greater than $36,000 but less than or equal to $38,000 D. Greater than $38,000
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
