Question: You are given the following information about activity D: Normal time = 10 weeks Crash time = 8 weeks Crash cost = $20,000 Cost to

You are given the following information about activity D: Normal time = 10 weeks Crash time = 8 weeks Crash cost = $20,000 Cost to crash per week = $1,500 What is the normal cost for activity D? $20,000 $17,000 $10,000 $14,000