Question: You are given the following three projects to decide. Project A Project B Project C RM RM RM Year 0 -??? -??? -??? Year
You are given the following three projects to decide. Project A Project B Project C RM RM RM Year 0 -??? -??? -??? Year 1 11 7 7 Year 2 6 11 6 Year 3 7 6 11 IRR 4.908% 4.572% 4.126% Cost of project 4.300% Note: RM-??? The amount of Initial Investment for the three projects is the same (a) Which project (projects) should be rejected based on the following status. Assuming (i) all projects are independent. (ii) all projects are mutually exclusive.
Step by Step Solution
There are 3 Steps involved in it
To decide which projects should be rejected based on the information provided we will compare the IR... View full answer