You are in the process of identifying risks on a construction project to build a large apartment building in the city. Which of the following risk events would be classified as an external risk event?
Group of answer choices
A. Heavy rains delay the construction of the foundation.
C. Activity duration estimates based on past performance are too short.
B. Vendors misinterpret the specifications for their work.
D. The available resources do not have the necessary skills.