Question: You are in the process of identifying risks on a construction project to build a large apartment building in the city. Which of the following
You are in the process of identifying risks on a construction project to build a large apartment building in the city. Which of the following risk events would be classified as an external risk event?
Group of answer choices
A Heavy rains delay the construction of the foundation.
C Activity duration estimates based on past performance are too short.
B Vendors misinterpret the specifications for their work.
D The available resources do not have the necessary skills.