Question: You are managing a project in which several requests have come in for changes to the scope. As part of the Integrated Change Control Process,
You are managing a project in which several requests have come in for changes to the scope. As part of the Integrated Change Control Process, which action would you refrain from doing?
Select an answer:
documenting the request
just making the changes
having all change requests approved
verifying the impact to the project's constraints