Question: You are managing a project that involves the following activities, with their respective durations and dependencies: Activity A: Duration 3 days, no dependencies. Activity B:

You are managing a project that involves the following activities, with their respective durations and dependencies:
Activity A: Duration 3 days, no dependencies.
Activity B: Duration 4 days, depends on the completion of Activity A.
Activity C: Duration 2 days, depends on the completion of Activity A.
Activity D: Duration 5 days, depends on the completion of Activities B.
Activity E: Duration 3 days, depends on the completion of Activity C.
Activity F: Duration 4 days, depends on the completion of Activity C.
Activity G: Duration 5 days, depends on the completion of Activity D, E, and F.
Activity H: Duration 6 days, depends on the completion of Activity F.
Calculate the Slack Time (S) for each activity. Insert the value for them in the table below.
Hint: To calculate slack time, you should use the Critical Path Method (CPM) to calculate the earliest start (ES), earliest finish (EF), latest start (LS), and latest finish (LF) times for each activity. You do NOT need to show your work for the ES, EF, LS, and LF for each activity.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!