You are managing a project using a new approach for your organization. three distinct phases are divided
Fantastic news! We've Found the answer you've been seeking!
Question:
You are managing a project using a new approach for your organization. three distinct phases are divided into several short iterations and each iteration will deliver a valuable product to the organization. what are these products best described as
a deliverables
b minimum business increment
c requirements
d minimum viable product