Question: You are managing a ten months project for pharmaceutical development; your 50 % of work was completed after four months of work. When you review
You are managing a ten months project for pharmaceutical development; your 50 % of work was completed after four months of work. When you review your expenditure, you found that you spent RM 250K. If your CPI is 0.9, what is your SPI?
(1 Point)
SPI = 0.9
SPI = 1.0
SPI = 1.25
None of the above