Question: You are overseeing a project to implement an accounting application for a dentist's office. In one of the performance meetings, you came up with the

You are overseeing a project to implement an accounting application for a dentist's office. In one of the performance meetings, you came up with the following measurement AC=500,PV=600, and EV=650. What is going on with this project?
Group of answer choices
Both CV and SV are positive numbers; thus, you are under budget and ahead of schedule.
You do not have enough information to calculate SPI and CPI.
The CV is a negative number, which means you have spent more than planned.
The SV is a negative number, which means the project is behind schedule.