Question: You are overseeing a project to implement an accounting application for a dentist's office. In one of the performance meetings, you came up with the
You are overseeing a project to implement an accounting application for a dentist's office. In one of the performance meetings, you came up with the following measurement ACPV and EV What is going on with this project?
Group of answer choices
A Both CV and SV are positive numbers; thus, you are under budget and ahead of schedule.
B You do not have enough information to calculate SPI and CPI.
CThe CV is a negative number, which means you have spent more than planned.
D The SV is a negative number, which means the project is behind schedule.