Question: You are performing an earned value analysis ( EVM ) on your 2 8 - week project. The project was scheduled to be 5 0

You are performing an earned value analysis (EVM) on your 28-week project. The project was scheduled to be 50% complete at this time. You have completed 14 of the 32 deliverbles (all of equal value). You have spent $28,000 of your original budget of $48,000. What is the estimated time to complete in weeks?