Question: You are performing an earned value analysis (EVM) on your 28-week project. The project was scheduled to be 50% complete at this time. You have

You are performing an earned value analysis (EVM) on your 28-week project. The project was scheduled to be 50% complete at this time. You have finished 14 of the 32 deliverables (all of equal value). You have spent $28,000 of your original budget of $48,000.

What is the Earned Value (EV)?

What is the Schedule Performance Index (SPI)?