Question: You are performing identify fisks on a software project. Two of your team members have spent half of the meeting arguing about Whether or not
You are performing identify fisks on a software project. Two of your team members have spent half of the meeting arguing about Whether or not a particular risk is likely to happen on the project. You decide to table the discussion but you aree concerned that your tearn's motivation is at risk. The next item on the agenda is a discussion of a potencial opportunity on the project in which you may be able to purchase a component for much less than it would cost to buald. Which of the following is Nor a good way to respond to an opportunity?
Explot
Share
Transfer
Enhance