Question: Youre performing Identify Risks on a software project. Two of your team members have spent half of the meeting arguing about whether or not a
You’re performing Identify Risks on a software project. Two of your team members have spent half of the meeting arguing about whether or not a particular risk is likely to happen on the project. You decide to table the discussion, but you’re concerned that your team’s motivation is at risk. The next item on the agenda is an discussion of a potential opportunity on the project in which you may be able to purchase a component for much less than it would cost to build.
Which of the following is NOT a valid way to respond to an opportunity?
A. Exploit B. Transfer C. Share D. Enhance