You are performing the Earned Value technique on a project after two months. Data appears below
\table[[,Actual cost,Earned value,Planned val],[Month 1:,75,000,65,000,100,000],[Month 2:,75,000,70,000,100,000]]
What is the cost variance (CV)?
50000
-15000
35000
-65000