Question: a. Using the derived data from above, calculate the following values: Schedule Variances Planned Value of Work Scheduled (PV) Earned Value (EV) Schedule Performance Index

a. Using the derived data from above, calculatea. Using the derived data from above, calculate the following values:

Schedule Variances

Planned Value of Work Scheduled (PV)

Earned Value (EV)

Schedule Performance Index (SPI)

Estimated Time to Completion

Cost Variances

Actual Cost of Work Performed (AC)

Earned Value (EV)

Cost Performance Index (CPI)

Estimated Cost to Completion

1) Using the following data, complete the table (monthly plan, activities plan, value, monthly actual, cumulative plan) and calculate the planned and actual monthly budgets through the end of June. Assume the project is planned for a 14-month duration and $280,000 budget. The figures in the table are in thousands of dollars. (You may place the figures on this table) Activity Jan Feb Mar Apr May Jun Plan %C Value Staffing 10 7 100 Blueprinting 4 6 85 Prototype Development 4 8 80 Full Design 3 8 10 90 Construction 10 30 50 Transfer 10 10 5 18 Monthly Plan Cumulative Monthly Actual Cumul. Actual 12 16 26 30 80 125

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!