Question: a. Using the derived data from above, calculate the following values: Schedule Variances Planned Value of Work Scheduled (PV) Earned Value (EV) Schedule Performance Index
a. Using the derived data from above, calculate the following values:
| Schedule Variances | ||
| Planned Value of Work Scheduled (PV) | ||
| Earned Value (EV) | ||
| Schedule Performance Index (SPI) | ||
| Estimated Time to Completion | ||
| Cost Variances | ||
| Actual Cost of Work Performed (AC) | ||
| Earned Value (EV) | ||
| Cost Performance Index (CPI) | ||
| Estimated Cost to Completion | ||
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
