Question: You are preparing a report to present to your project executives who are mainly concerned with understanding where the major milestones are. What level of

You are preparing a report to present to your project executives who are mainly concerned with understanding where the major milestones are. What level of schedule will you use?
Group of answer choices
Level 1- Milestone Level Schedule
Level 3- Baseline Schedule
Level 2- Bid/Proposal Schedule
Level 5- Weekly Work Plan Schedule