Question: You are presented with the following problem that involves the design and launch of an engineered product by a company in NSW , Australia. Table

You are presented with the following problem that involves the design and launch of an engineered product by a company in
NSW, Australia.
Table 1:
Activity
ID Activity Description Duration Predecessors Resources
1 Customer requirements 30 days - PRDT
2 Define design goals 10 days 1 DSGN[2], PRDT, QUAL ,MANU
3 Preliminary product design 20 days 2 DSGN[2], QUAL, MANU, ENGA[2], PRDT
4 Preliminary process design 15 days 3 QUAL, DSGN, ENGA, PROC
5 Develop engineering drawings 15 days 2 DSGN[2], ENGA[3], QUAL
6 Develop material specifications 10 days 5 DSGN[2], ENGA[2]
7 Find suppliers 15 days 6 DSGN, SUPL, ENGA
8 Order prototype material 5 days 7 SUPL, ENGA[2]
9 Receive prototype material 40 days 8
10 Assembly line fixtures 20 days 4 MANU, PROC, DSGN, ENGA[2]
11 Preliminary product cost 5 days 7 FINA
12 Set up assembly line 15 days 10 MANU, PROC, ENGA[2]
13 Set up test equipment 15 days 12FF ENGA[2], QUAL
14 Build prototype 10 days 9,12,13 DSGN, ENGA[3], MANU, SUPL
15 Test Prototype 40 days 14 QUAL, DSGN[2], ENGA[2]
16 Update engineering drawings 10 days 15 DSGN, ENGA[2]
17 Update process design 10 days 15 PROC, DSGN[2], ENGA[2]
18 Order production material 5 days 16 SUPL, MANU, DSGN
19 Receive production material 40 days 18
20 Develop quality system 5 days 19FF QUAL
21 Develop packing specifications 5 days 16 DSGN[2], ENGA[2], QUAL
22 Conduct production trial run 5 days 17,19,21 QUAL, MANU, PROC, DSGN, ENGA[2]
23 Conduct product validation test 40 days 22 DSGN[2], ENGA[2], MANU
24 Finalise engineering drawings 10 days 23 DSGN[2], ENGA[2]
25 Finalise process design 10 days 22 PROC, DSGN, ENGA
26 Production build 5 days 24,25 DSGN, QUAL, PROC, ENGA[2]
27 Ship parts for customer validation 5 days 26 SUPL, PROC
Table 2:
Resource (staff) Abbreviation Availability Rate/Hour
Product Management PRDT 1 $150
Design Engineering DSGN 2 $100
Quality Engineering QUAL 1 $90
Process Engineering PROC 1 $80
Supply Chain Management SUPL 1 $80
Manufacturing MANU 1 $90
Finance FINA 1 $100
Engineering Assistant ENGA 3 $80
Project Infrastructure (Overhead Costs) OH $10
# Consider overtime penalty rate as 50%
Section A: Instructions for Completing the MS Project Tasks and Interpretation of Results:
1. Create a new file and enter the project title. Ensure the author's name and student number are entered in the appropriate field to
be displayed in all printouts and reports. Ensure all text within charts is reasonably legible.
2. Fix the start of the project to your birth date next year. Include this in your assumptions list.
3. Set the environment to a 40-hour week, 5 working days per week, and the working day starts at 8 am. Account for any nonworking times and public holidays, as applicable to NSW. Include a graphic in the report to show that you have entered all the
holidays in the project calendar.
4. Create the resources sheet with the appropriate resource type, maximum availability and pay rates, as applicable.
5. Enter the tasks, durations and dependencies.
6. Enter the resources. Produce a Gantt chart to include in your report.
7. View the Resource Graph and note any over-allocations. Generate a report for each of the resources concerned, to clearly show
over-allocations. If a particular resource is not showing any over-allocations, make sure to identify them in the report as such.
8. Investigate appropriate levelling options within MS Project for the following scenarios and keep a record of the options
applied in each scenario. Note the effect on project duration and cost in each scenario. Produce Gantt charts and project statistics#
for each scenario to include in your report.
I. Resource-constrained: completing the project within the shortest possible time without adding more resources (i.e.
explore levelling options within MS project)
II. Time-constrained: completing the project by the initial completion date (as in step 6) at the lowest possible cost.
a) by bringing in the minimal required amount of additional resources
b) by allowing relevant resources to work overtime
9. Produce a cost report for this project, showing the costs at activity, resource and project levels to include in the report. Only
include elements of the report that convey useful information to the reader.
Section B: Assessment Report You are required to submit a PDF copy of your report, along with MS Project files
The report shall be a focused discussion of the issues involved, solutions proposed, and lessons learnt in completing the exercise,
and must demonstrate an understanding of the use of MS Project as well as its limitations, as you experienced. The report should
follow the format of a typical technical report (using a structure with appropriate headings and a table of contents; include the
word count on the title page). An introduction, problem definition, the solution approach followed and a discussion of t

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!