Question: You are project manager for a project with activities, predecessors, normal durations, normal costs, crash durations and crash costs as shown below. a ) What
You are project manager for a project with activities, predecessors, normal durations,
normal costs, crash durations and crash costs as shown below.
a What is the project's Earliest Finish EF time and total cost as originally
scheduled assuming normal durations and normal costs
b Can the project duration be reduced to weeks? If so what activityies would
you recommend crashing to get it to that duration? What is the minimum total
project cost to finish within this duration?
c Can the project duration be reduced to weeks? If so what activityies would
you recommend crashing to get it to that duration? What is the minimum total
project cost to finish within this duration?
d Can the project duration be reduced to weeks? If so what activityies would
you recommend crashing to get it to that duration? What is the minimum total
project cost to finish within this duration?
e What is the minimum duration the project can possibly be completed in What is
the minimum total cost to complete the project within this amount of time?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
