Question: In a job shop operation, four technicians can work on any of the four machines. The time required, in minutes, for each technician to
In a job shop operation, four technicians can work on any of the four machines. The time required, in minutes, for each technician to complete the work on each machine are presented in the following table. Technician Machine 1 Adam 40 Brian 30 Chong 45 David 40 Machine Machine 2 Machine 3 Machine 4 40 50 40 45 40 35 40 35 45 35 45 30 (i) Find the optimal assignment that will minimize the total time taken. (ii) Compute such minimum time. (8 marks) (2 marks) (10 marks)
Step by Step Solution
3.49 Rating (149 Votes )
There are 3 Steps involved in it
Question Step 1 Subtract the lowest number of each row from rest numbers of that row M1 M2 M3 M4 ADA... View full answer