Question: You are the new project manager tasked with taking over for a projectmanagerwho left six weeks ago. Some of the numbers that you find in
- You are the new project manager tasked with taking over for a projectmanagerwho left six weeks ago. Some of the numbers that you find in your initial research are as follows:
A)Estimated project cost: $675,000
B)Project timeline: 24 weeks
C)This is week 16 and accumulated costs are $300,000.
D)Additionally, only 25% of the work has been completed.
What is the cost variance?
What is the schedule variance?
What will be the estimated costat completion?